Day 3
May 25, 2001

Construction of the site continued.  
Well drilling rig arrived on the scene in the afternoon.

 

Day 4
May 26, 2001
Drilling began at about 7:00 a.m. The conductor casing was installed and concrete was poured around the conductor casing to a depth of 20ft. After the concrete was set, drilling proceeded. 


Drilling Begins

Day 5
May 27, 2001
Hard rock was hit at about 175 ft.  Drilling is slowed.

 

Day 6
May 28, 2001
A collar was added to the drill to speed up drilling process