Well drilling rig arrived on the scene in the afternoon.
Day 4
May 26, 2001
Drilling began at about 7:00 a.m. The conductor casing was installed and
concrete was poured around the conductor casing to a depth of 20ft.
After the concrete was set, drilling proceeded.
Drilling Begins
Day
5
May 27, 2001
Hard rock was hit at about 175 ft.Drilling
is slowed.
Day
6
May 28, 2001 A
collar was added to the drill to speed up drilling process