Swan Lake
hydro project meeting set
Public hearing on $2 billion private
project set for Wednesday at the government center
By LEE JUILLERAT,
Herald and News 5/24/11
Symbiotics, which
has offices in Portland, Bend and Utah, Idaho and Texas,
is proposing the 1,380-megawatt Swan Lake North Pumped
Storage Hydroelectric Project on 530 acres of Bureau of
Land Management land about 11 miles northeast of Klamath
Falls.
Erik Steimle,
environmental compliance director from Symbiotics’
Portland office, said the project is designed to store,
not generate, power.
“The project is
still in its early stages,” he said, noting the company
plans to do traffic, wildlife and
geological surveys
this summer.
Steimle said the
proposed project boundary runs from the east side of
Grizzly Butte to about a mile east of the Swan Lake Rim.
Two reservoirs
The project will
include two 8,500 acre-feet reservoirs and a
5,860-foot-long steel penstock to move water back and
forth between the reservoirs and connect to 10
generating pump-turbine units in a powerhouse with a
generating capacity of 1,144 megawatts.
When excess wind or
solar power is created, excess energy capacity will pump
water uphill from the lower reservoir to an uphill
reservoir. When energy demand increases, the stored
water will be released to the downhill reservoir through
powerhouses.
The reservoirs will
be created by two earth embankment dams, one 70-feet
tall and 11,850-feet long, the other 80-feet tall and
8,415-feet long. Steimle said water would be provided
from existing groundwater wells.
Side Bar
1,500 acre-feet
annually
Estimates call for
1,500 acre-feet of water annually. The reservoirs would
be lined with clays or a manmade membrane, depending on
study recommendations, to reduce groundwater seepage.
A 12.5-mile long
500-kilowatt line would interconnect with a proposed
upgrade to an existing 500-kilovolt line with power
distributed primarily to California and local utilities,
according to the application.
Additional
information is available at the Federal Energy
Regulatory Commission website at www. ferc.gov/docs-filing/ecomment.asp.
|