USGS studies sediment issues with Elwha Dam removal to inform future river restoration projects,

CB Bulletin 10/16/12
 

The largest dam-removal project in history has increased river water cloudiness caused by suspended particles, known as turbidity, a process that could affect aquatic life.

The dismantling of two large dams on the Elwha River in Washington began in September 2011 and has increased river turbidity significantly, even though most of the sediment trapped behind the dams has yet to erode into the river.

These findings appear in the first published report http://www.agu.org/pubs/pdf/2012EO430002_brr.pdf on sediment response to the Department of Interior’s Elwha River Restoration Project.

"The construction of dams can cause major disruptions to natural processes on riverways, and we can expect their removal to also have anomalous effects for some time until rivers regain their equilibrium," said USGS Director Marcia McNutt. "What we are learning from the response of the Elwha River ecology to increased sedimentation during dam removal will help guide other large dam removal and river restoration projects in the future."

The U.S. Geological Survey authors examined sediment and water-flow data from the first six months of dam removal and found that dam-removal activities and natural processes both affected the river’s turbidity. Breaching of several temporary earthen dams built to assist with deconstruction caused sustained increases in downstream turbidity. High river flows associated with rainfall also increased turbidity, at measuring stations both above and below the dams.

"During the first six months of dam removal, most of the sediment released was silt and clay, which caused substantial -- but not unexpected -- turbidity in the river and coastal waters. As dam removal progresses we expect more and more sand and gravel to be released into the river, which will likely help build river bars and slow coastal erosion near the Elwha River mouth," said Jonathan Warrick, lead author of the report and research geologist for the USGS. "Although the river has been quite turbid since dam removal began, most of the sediment-transport action is yet to come."

High turbidity levels can reduce the amount of light penetrating river and coastal waters, which can inhibit aquatic plant growth and affect wildlife that rely on sight to find food and avoid predators.

Removal of the dams is exposing more than 24 million cubic yards of sediment stored in the reservoirs, enough to fill the Seattle Seahawks' football stadium eight times. Using a combination of measurements from a station downstream of the dams, the authors estimated that less than 1 percent of the 24 million cubic yards of sediment stored behind the dams had eroded and moved downstream. Thus, the authors conclude that completion of dam removal in 2012–2013 will expose much more sediment to erosion, resulting in continued turbidity downstream as well as changes in the shape and sedimentary makeup of the riverbed and the coastal landforms around the mouth of the river into the Strait of Juan de Fuca, which is only 5 miles below Elwha Dam.

"Tracking these changes will be important to assessing their effects on habitat for fish and other wildlife in what historically was one of the most productive salmon rivers in Puget Sound," said Warrick. Scientists expect dam removal to cause short-term adverse effects on aquatic life, followed by large-scale ecosystem resurgence once the river’s sediment load returns to a more normal and natural state.

The authors' findings are contained in a brief report in the Oct. 23 issue of Eos, Transactions, American Geophysical Union.

Dam decommissioning has become an important means for removing unsafe or obsolete dams and for restoring rivers to a more natural state. Two dams are being removed incrementally during this 2-year project: the 105-foot-high Elwha Dam impounding Lake Aldwell and the 210-foot-high Glines Canyon Dam impounding Lake Mills.

Only part of the total sediment stored behind the dams -- 9 to 10 million cubic yards -- is expected to erode into the river and move downstream to coastal areas. The methods and schedule of dam deconstruction are largely governed by management of this sediment, with controlled drawdowns of the reservoir levels to prevent deleterious impacts of an abrupt release.

====================================================

In accordance with Title 17 U.S.C. section 107, any copyrighted material herein is distributed without profit or payment to those who have expressed a prior interest in receiving this information for non-profit research and educational purposes only. For more information go to: http://www.law.cornell.edu/uscode/17/107.shtml

Home Contact

 

              Page Updated: Friday October 26, 2012 11:45 PM  Pacific


             Copyright © klamathbasincrisis.org, 2001 - 2012, All Rights Reserved