Fish ladder needs one more
piece
Wednesday, December
22, 2004 2:02 PM PST
Published December 22,
2004
By DYLAN DARLING
Crews working on a
new fish ladder at the Link River Dam will
take a break later this month while they wait
on a final part for the project to arrive.
Work on the $3.2 million ladder is nearly
done, but won't be complete until one last
part is installed by crane in mid-January,
said Cecil Lesley, water and land chief at the
U.S. Bureau of Reclamation's Klamath Falls
office.
"When that is in, it
will be ready to rumble," he said.
Construction of the ladder, which started last
summer, fell a couple of weeks behind schedule
when work crews had trouble keeping water from
busting through temporary dams put in to dry
out the work site.
The dam problems
were solved by August, and the ladder was
supposed to be finished by year's end. The
crews almost made that mark, but because of
the unavailability of a control part of the
dam, they will have to wait to finish in
January.
Once completed, the 360-foot-long ladder will
allow fish - including endangered Lost River
and shortnose suckers - to climb the 10 feet
needed to get from the Link River to Upper
Klamath Lake.
The same
construction company, Slayden Construction of
Stayton, that built the $16 million A-Canal
headgates, is working on the concrete fish
ladder.
Built in 1921, the Link River dam already has
a fish ladder, which was designed to provide
passage for redband trout and installed in
1926. Federal officials deemed the old ladder
inadequate for sucker passage.
While the ladder has
been under construction, the north half of the
Link River Nature Trail has been closed. The
section of trail was originally going to open
again late this month, but will remain closed
until the construction is finished, officials
said. |