Our Klamath Basin
Water Crisis
Upholding rural Americans' rights to grow food,
own property, and caretake our wildlife and natural resources.
Letter from John and Loy Beardsmore to FERC and PacifiCorp
regarding PacifiCorp and Klamath Dam Removal
FOLLOWED BY Response from PacifiCorp August 20, 2020 Mr. Scott Bolton Senior VP, External Affairs & Customer Solutions PacifiCorp Energy 825 N.E Multnomah, Suite 1500 Portland, OR 97232
Mr. Mark A. Sturtevant
Managing Director, Hydro Resources PacifiCorp Energy 825 N.E. Multnomah, Suite 1500 Portland, OR 97232
Ms. Kimberly D. Bose Secretary
Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426
RE: Klamath Project (Project No. P-2082), and the Lower
Klamath Project (Project No. P-14803)
Dear Secretary Bose and Members of the Commission,
We would like to thank the Commission for their wisdom that
there are significant levels of uncertainty with the Klamath
Project concerning the technical capacity, but more
importantly, the limited finances of the Klamath River
Renewal Corporation. We’ve long held the belief that costs,
not only could, but most certainly would, rise above the
amounts estimated and provisioned for dam removal. We’ve
also repeatedly pointed out to the Commission that the
KRRC’s contractors cannot perform the most basic tasks
associated with preparation for dam removal, such as
groundwater well-monitoring, work schedule notifications,
answering landowners concerns and questions, etc. We’ve also
challenged many of their plans for revegetation, fire
management, and logistics, just to name very few of our
apprehensions with their lack of technical experience and
abilities. We thank the Commission for recognizing our
concerns and we agree that requiring PacifiCorp remain as a
co-licensee is in the public’s best interest.
In just one month’s time, since the Commission’s ruling, we
have seen a flurry of attempts by dam removal proponents
such as, Governor Newsom (the same governor that is
lamenting power blackouts and consequences of wildfire and
challenges of fire suppression), and Congressman Huffman, in
a grand-standing effort, attempted to use his sub-committee
chair position to call a meeting with supposed experts to
pressure PacifiCorp to becoming a co-licensee. These
‘experts’ are Tribal Leaders and other interested parties
only concerned with removal of the dams. They all are
attempting to pressure Warren Buffet to immediately accept
becoming a co-licensee, as any time delays will threaten the
finances of the project. This fortifies our arguments that
the financial resources of the KRRC were always precarious,
and as time goes on, even more so. Most recently Tribal
Representatives have become so desperate that they are
threatening Buffett with litigation, yet we all recognize
that if dam
removal were to move forward, if it was an environmental
disaster as we predict and the fisheries were to be
decimated, the Tribes would also litigate.
As much as we are heartened by the Commission’s decision, IF
PacifiCorp agrees to become a co-licensee, our concerns for
dam decommissioning are not allayed. We have examined the
Condit Dam removal and lessons learned. Unfortunately, the
same sediment modeling calculations used for the Condit,
have been used to model sediments behind the Klamath
Project. While estimated at 20-30 million cubic yards of
sediment behind the project, as in the Condit, this will be
off by a factor of two, resulting in actual sediment amounts
being closer to 40-60 million cubic yards of sediment. No
amount of dam removal experience can envision that amount of
sediment will magically travel over 230 miles down the river
and flow out into the ocean without decimating spawning
beds, creating flooding issues, and sedimentation issues at
the mouth of the Klamath River requiring dredging operations
for the harbor at Crescent City and the river delta. These
amount of sediment deposits will most surely negatively
affect the fisheries. Inadequate studies of the possible
toxicity of the sediments is concerning as well. This
sediment deposition alone will require river restoration at
a cost of billions of dollars, if at all possible.
If sediment issues were not enough for concern, local Copco
residents are concerned about losing their wells, slope
stability, increased fire danger with no plans for true
mitigation, as there is no way to mitigate the loss of the
reservoirs. Communities downstream of the dams are
justifiably concerned with flooding issues. The City of
Yreka would need to have their water line replaced prior to
dam decommissioning. Siskiyou County has many concerns, the
least of which is loss of tax revenue if dam removal were to
move forward that would lead to bankruptcy. These are just a
few of the liability concerns with dam removal.
Yes, we are encouraged that PacifiCorp would be required to
sign on as a co-licensee. At the very least, it gives all
the parties above a reliable licensee to assume liability of
any negative consequences of dam decommissioning. It has
always been understood that after dam removal that the KRRC
would disappear. At least we know that PacifiCorp is here to
stay and would ultimately bear the entirety of any liability
issues left behind for unproven environmental benefits.
Respectfully submitted,
Loy and John Beardsmore
============================================== Response from PacifiCorp Dear Ms. and Mr. Beardsmore, Thank you for including PacifiCorp in your correspondence regarding the Federal Energy Regulatory Commission’s July 16, 2020, ruling on the proposed license transfer for the Klamath dams as part of the Klamath Hydroelectric Settlement Agreement. Your informed expression of your concerns is a valuable part of the public and regulatory oversight process that must accompany and shape the outcome of something as big and impactful as the proposed removal of the Klamath dams. I want to assure you the company takes seriously the concerns you have raised about possible project impacts to your property and Klamath River communities. PacifiCorp has always viewed the KHSA as establishing a process that could lead to removal of the dams if certain conditions are met. Part of the process the amended KHSA established is a requirement that the main federal energy regulator examine and approve both the license transfer and, ultimately, dam decommissioning plans to ensure that the proposal is in the public interest and will satisfy safety, environmental, economic, and other standards and requirements. PacifiCorp was disappointed in the FERC ruling, which undercuts a key component of the settlement the company negotiated to protect our electricity customers across six states from uncertain costs and risks associated with dam removal or relicensing. At the same time, FERC’s order suggests that the concerns you’ve raised will be taken seriously and not brushed under the rug. Our experience as an energy company that owns and operates hydro projects around the West and dozens of federally-licensed power plants further informs our belief that rigorous oversight should, and will, be part of any plan involving the dams. PacifiCorp is continuing to talk to engage our settlement partners, regulators and, importantly, our customers to evaluate a path forward that protects our customers across the states we serve. I want to reiterate that I believe many of the concerns you raise need to be fully examined as part of any decommissioning, regardless of who is ultimately responsible for the work. I also want to acknowledge again your continued involvement to raise the concerns of your community in a thoughtful and effective way. Sincerely, Scott D. Bolton Senior Vice President External Affairs and Customer Solutions
==================================================== In accordance with Title 17 U.S.C. section 107, any copyrighted material herein is distributed without profit or payment to those who have expressed a prior interest in receiving this information for non-profit research and educational purposes only. For more information go to: http://www.law.cornell.edu/uscode/17/107.shtml |
Page Updated: Monday September 14, 2020 01:50 AM Pacific
Copyright © klamathbasincrisis.org, 2001 - 2020, All Rights Reserved