HERE These are the notices we have received---they overlap a bit: The Contested Case proceedings for the COB Energy Facility have been going on during June and July by correspondence. Various attorneys and expert witnesses have been submitting required filings, affadavits and responses. There have been telephone calls and e-mails to set up the schedule for the cross examination phase which will take place July 28th at 9 a.m. in County Commissioners hearing room in Klamath Falls at 305 Main Street, Room 219. Although there will be no opportunity at this hearing for public comment, we are all invited to come and watch the proceedings.
There
are a number of additional steps after the
cross-examination concludes before the Hearings
Officer makes a decision. Attorneys submit final
briefs in mid-August. The Hearings Officer is
scheduled to issue her proposed order on September
3. Then the parties file "exceptions" which are
objections to the Hearings Officer Order. Then
the Energy Facility Siting Council holds a hearing
and makes a decision probably in mid-Oct.
July 26, 2004 After a final telephone conference today
to schedule witnesses, it appears that this hearing
will not take three days. Those of us opposed to
the facility being sited in Langell Valley have
submitted legal evidence and affadavits on some
points that COB has not addressed. It is better in
some cases not to get their witnesses on the stand.
After the schedule was set for the witnesses being
called, it appears that this part of the proceedings
may not take three days,
in fact it might be able to be completed in one day.
So if you plan to attend we encourage you to be
there Wednesday. It is scheduled to begin at 9 a.m.
The only witness scheduled at a time certain is
Jerry Grondin of Oregon Water Resources and he is
scheduled for 2 p.m.
Klamath County Board
of Commissioners has scheduled meetings to discuss
the proposal of extending the current Enterprise
Zone out Hwy. 140 E and Hwy. 70 to the proposed
COB Plant site.
The meetings: first
at Klamath Falls City Council - Monday, Aug. 16th,
7 pm at the Klamath Falls City Council Chambers;
Klamath County
Commissioners will hold another meeting on
Tuesday, Aug. 24, 10 am, at the Klamath County
Commissioners Hearing Room.
People's Energy has
requested the Enterprise Zone be extended to the
site, and is also requesting a tax break for 15
years in return for a commitment of paying $1
million a year for the 15 years to Klamath
County. People's Energy would save an estimated
$71.3 million in taxes on the project during that
same period.
The above information
was obtained from the Herald & News, so please
call the Commissioners office to verify dates and
time in case changes are made.
From Cindy Deas
|